FORM VI - Regular Certificate to run a boiler after steam test

Download


Form VI
Counterfoil D.B.No……………...
No. DBL
Registry Number of Boiler Type of Boiler
Boiler Rating Place and year of manufacture
Name of Owner
Situation of Boiler
Repairs
Remarks
Hydraulically Tested on……………. to ……………………… kgs/lbs. per sq. cms/inch

Maximum pressure permitted………….kgs/lbs. lo the square cms/inch for the period from ………… to ……………………. The loading of the ……………………….. safety valve not to exceed ……………………………………………. The main steam pipe tested hydraulically to a pressure of ……………….. kgs/lbs. per square cms/inch ast on …………. Fee Rs …………………. Paid on ……………………… Dated at ………… DELHI …………………………. This …………………………. Day of ……………. 19




Countersigned

Inspector Chief Inspector
 
No. DBL D.B. No …………….
Certificate For The Use Of A Boiler
   
Registry Number of Boiler Type of Boiler
Boiler Rating Place and year of manufacture
Name of Owner
Situation of Boiler
Repairs............................................................................................................ ........................................................................................................................
Remarks .......................................................................................................... .........................................................................................................................

Hydraulically Tested on........................ to.................. Kgs/lbs. sq. cms/inch. I hereby certify that the above described boiler is permitted by (me) ................(the chief Inspector) under the provisions of Section 7/8 of Indian Boilers Act. No V of 1923, to be worked at a maximum pressure of .................. Kgs/lbs. to the square cms./ inch for the period from ................ to .................... The loading of the ............................safety valve is not to exceed................................................................................................

I further certify that the main steam pipe was tested hydraulically to a pressure of ………………….. kgs/lbs per square cms/inch last on ………………………….. Fee Rs …………………………. Paid on ………………………….. Dated at Delhi ……………. This ………………………… day of …………………………….. 19 .



Countersigned

Inspector Chief Inspector


 
No structural alteration, addition or renewal shall be made to the boiler other-wise than in accordance with Section 12 of the Act.

Under the provisions of Section 8 of the Act. this certificate shall cease to be in force :

(a) On the expiry of the period for which it was granted; or
(b) When any accident occurs to the boiler; or
(c)

When the boiler is moved, the boiler not "being vertical boiler the heating surface of which is less than two hundred square feet, or a portable or vehicular boiler; or

(d) When any structural alteration, addition or renewal is made in or to the boiler; or
(e)

If the Chief Inspector in any particular case so directs when any structural alteration, addition or renewal is made in or to any steam pipe attached to the boiler; or

(f)

On the communication to the owner of the boiler of an order of the Chief Inspector or Inspector prohibiting its use on the ground that it or any Steam pipe attached thereto is in a dangerous condition.

Under Section 10 of the act, when the period of a certificate relating to a boiler has expired, the owner shall provided that the he applied before the expiry of that period for a renewal of the certificate, be entitled to use the boiler at the maximum pressure entered in the former certificate pending the issue of orders on the application, but this shall not be deemed to authorize the use of a boiler in any of the cases referred to in clauses (a), (b), (c), (d), (e) & (f) of Sub-section (1) of section 8 occurring after the expiry of the period of the certificate.

The boiler shall not be used at a pressure greater than the pressure entered in the certificate as a maximum pressure nor with the safety valve set to a pressure exceeding such maximum pressure.

The boiler shall not be used otherwise than in a condition which the owner reasonably belives to be compatible with safe working.

N.B.- The particulars and dimensions regarding this boiler may be obtained by the owner on payment in the prescribed manner on application to the Chief inspector.
Latest News
 
Advertisement 47APP on contract basis
Automated System of Allotment Govt. of Delhi (e-Awas)
Budget-19-20
Delhi Budget 2017_18
Discontinuation of physical printing of Government of India Gazettes
Draft Delhi Road Safety Policy
Economic_survey-2018-19
Empanelment of Ms ICSIL for hiring of contractual manpower
Extention of date Application for the post of Other Persons Members for Lok Adalats
Guidelines for Modal RFP Documents
 
Local Services
 
 
Important Links
 
Online Complaint Registration
On Line Services For Directorate Of Employment
Jeevan Centers for Convenience
On Line Registration for Shop And Establishment
 
Last Updated : 08 Jan,2019
Contact for Help/Grievance Redressal | Vacancy | Messages|RTI Act 2005